Interpretation of the construction of photovoltaic power stations in Henan Province

Recently, the Henan Provincial Development and Reform Commission issued the Notice on Promoting the Construction of Photovoltaic Power Plants to 18 prefecture-level cities in Henan Province. After careful reading by reporters, this article has the following highlights:

1. Construction of photovoltaic power stations in Henan Province is temporarily not subject to the National Energy Agency's targets. This favorable condition will stimulate the development of photovoltaic projects in Henan Province.

The reporter visited a number of photovoltaic companies. Most companies believe that this policy can improve the construction speed of Henan Province to a certain extent. However, various photovoltaics generally believe that this policy has various concerns for investing in photovoltaic projects in Henan Province. First, the National Energy Administration only Given the construction index of 750 MW in Henan province, the competition for the construction of photovoltaic projects in other provinces across the country is very fierce. The introduction of such a policy in Henan is nothing more than a benefit for the photovoltaic industry and photovoltaic companies. However, there are various kinds of assistance in actual operations. Not being indexed means that the Henan Provincial Development and Reform Commission will not distribute indicators to all PV companies, and Henan Electric Power Company will not be able to promote project evaluation and project management. The reporter visited the Henan Electric Power Company. As of July 15, the Henan Electric Power Company did not have the opportunity to review the system's access plan for the 2014 PV project. All photovoltaic projects stopped. Detailed inquiry revealed that the development of Henan Province has changed. The CPC and the provincial power company had differences in the project indicators. The provincial power company only recognized the 750 MW issued by the state and the Provincial Development and Reform Commission wrote that it was not controlled by the national indicators. The two parties are currently visiting a household through a reporter during further consultations. One of the photovoltaic company's project leaders in Neihuang County said that if the Provincial Development and Reform Commission and the provincial power company did not coordinate PV projects across the province in August this year, many of the projects will be empty and the photovoltaic projects in Henan Province will be difficult. carry out.

Second, in order to speed up the construction of distributed power generation projects in Henan province, the provincial government issued mandatory regulations for the Wenwen document. When applying for the record, each city must be constructed in accordance with the 2:1 ratio of distributed and ground power stations.

For such a bundled construction policy, the reporter learned that this policy is impossible to achieve in some prefecture-level cities because some prefecture-level cities do not have mature rooftop construction ground power stations and do not have suitable land. The reporter of the Henan Provincial Development and Reform Commission's filing website has detailed statistics for most of the companies favoring the development of ground-based photovoltaic power plants. However, the situation of distributed filing and construction is not optimistic. If such a ratio is not met, many prefecture-level cities will not be able to follow the two. : 1 matching construction. Many photovoltaic companies building ground-level power stations are concerned that other enterprises will not complete the construction of distributed power stations will drag their own companies to complete the construction of ground power stations because the documents exceed the ratio of the provisions of the project do not enjoy state subsidies.

Third, the document clearly stipulates who joins the network first who enjoys the national indicator. This policy has many problems encountered in the actual operation process, because the provincial power company does not accept the project access plan that is not within the scope of the indicator. Review. In the actual construction process can not advance the project construction.

4. It is clearly stated in the document that the projects that acquired the preparatory road strips from 2013 to 2014 will be given priority for inclusion in this year's construction plan.

The development of photovoltaic projects in Henan is entirely based on the photovoltaic policy of Henan Province. Some companies are excited to invest in Henan for project development. However, many PV companies have been waiting and waiting.